    Have you ever had this problem.

    Rick draws the plan, making sure everything is on snaps.
    4" snaps for the walls, 12" snaps for the dims.

    Rick emails the drawing to ken, who adds a few things (moves NOTHING)
    and send it back to Rick.

    Rick opens the drawings and guess what, the walls al no longer on snap.

    Am I going insane here?
    Thanks,
    jojo
     
    jojo, Aug 15, 2006
    #1
  2. jojo

    Carl AK Guest

    Check coordinates of lines, maybe no entities have shifted, maybe
    SNAPBASE was moved (from 0,0,0)?
     
    Carl AK, Aug 15, 2006
    #2
  3. jojo

    jojo Guest

    Thank you carl, I will look at that!

    jojo
     
    jojo, Aug 15, 2006
    #3
  4. Try Ockham's Razor....

    Did someone change the UCS?
     
    Michael Bulatovich, Aug 16, 2006
    #4
  5. jojo

    jojo Guest

    My first thought. We routinely change our ucs to work on elevations, but the
    ucs's are preset and all based on the same 0,0 point. I checked the drawing
    myself, and determined the 0,0 was still where it was supposed to be...but
    the drawing was off.
    ;-(